Residential Development Oldtown Woods – Celbridge

252 Unit Development

Company Role:

Main Civils Contractors

Developer:

O Flynn Group

  •  

Enabling Works

  • Site Strip and reduce levels across the entire site
  • Soil stabilization – 140,000m3 including all certification & sign off on completion to Consulting Engineer’s requirement (Donnachadh O Brien & Associates-Alan Lambe)
  • Removal of unsuitable material off site to EPA licenced landfill – circa. 45,000m3
  • Removal & clearing of all site vegetation incl. tree felling to EPA licenced landfill

Site Development:

  • Main line drainage both Storm & Foul inclusive of all testing requirements and installation of Manholes – Taking in charge to new Foul network (Uisce Éireann) & Storm Water Network(Kildare Co Co) handover & sign off by mentioned stakeholders.
  • Watermain including testing chlorination & taken in charge / sign-off by Uisce Éireann.
  • Roads, Tar, Line Marking, Footpaths
  • ESB, Telecoms, Fibre Ducting Street lighting to all house units & roads.
  •  

House Curtilage:

  • House Foundations
  • Internal & External house drainage
  • Placement of UÉ Inspection chambers
  • Floors, Insulation, Radon
  • Footpaths externally , Paving ,Boundary walls and Fencing & Gates to rear gardens
  •  